A preventive maintenance schedule lists every servicing job your gear needs and when each one is due, so the work happens before a failure instead of after it. This guide gives a starting schedule for a commercial dive spread, item by item: helmets and masks, regulators, cylinders, compressors, umbilicals, gauges and the rest of the kit.
Read this first. The intervals below are typical, not rules. Your schedule must follow the manufacturer’s instructions for each item and the code and regulations that apply to your work, such as CSA Z275.2, the federal diving rules or your provincial regulation. Where they differ, use the shorter interval.
How to build a preventive maintenance schedule
- List every item. One row per helmet, regulator, cylinder, compressor, umbilical and gauge, each with its own ID and serial number. The equipment maintenance log template has a register sheet for this.
- Take the jobs from the manual. Each manufacturer publishes what to inspect, what to replace and how often. Under the federal rules, diving equipment is inspected, tested, maintained and calibrated by a qualified person at the intervals the manufacturer recommends (section 18.26).
- Check the regulations. Some intervals are set in law. In BC, for example, scuba cylinders need a hydro at least every five years and an internal visual inspection every year (WorkSafeBC section 24.39).
- Use the shortest interval that applies, and write down where it came from.
- Set a warning period. Thirty days is enough to order a service kit or book a test facility.
- Keep pre-use checks separate. Checks done before every dive belong on your dive site checklist. The schedule holds the jobs that have a due date.
Typical schedule for dive gear, item by item
| Item | Typical servicing jobs | Typical interval | Where it comes from |
|---|---|---|---|
| Helmets and full face masks | Function check; periodic inspection; overhaul with the manufacturer’s parts kit | Before each use; as the manual sets, often monthly checks and an annual overhaul | Manufacturer |
| Non-return valves on helmets and masks | Check in line with the manufacturer’s instructions | Daily, before diving starts | Federal rules for surface supply dives (section 18.60); manufacturer |
| Scuba regulators and bailout first stages | Function check; service with kit | Before each use; usually yearly, or by number of dives | Manufacturer |
| Scuba and bailout cylinders | Internal visual inspection; hydrostatic test | Visual yearly; hydro every 5 years for most steel and aluminium cylinders | WorkSafeBC 24.39 in BC; the test period marked on the cylinder |
| Cylinder valves | Service, O-rings, burst disc check | With the visual inspection | Manufacturer |
| Breathing air compressors | Oil level and condensate drains; filter cartridge change; oil change; scheduled service | Daily; by running hours as the manual sets | Manufacturer |
| Compressor and filter system air quality | Air quality test by a lab | At least yearly | Federal rules (section 18.24); WorkSafeBC 24.26 |
| HP storage banks and volume tanks | Visual inspection; pressure test | As marked on the vessel | Vessel markings and your provincial pressure vessel rules |
| Umbilicals and hoses | Visual check; periodic pressure test and inspection of fittings | Before each use; periodic test at the interval in your code | Code and manufacturer |
| Depth gauges, pneumofathometers, panel gauges | Test and calibration | Every 6 months, or when a fault is found | WorkSafeBC 24.29 in BC; manufacturer |
| Dive control panels and gas manifolds | Leak and function test; service | Before each job; yearly service | Manufacturer |
| Diver communications | Function check; service | Before each use; as the manual sets | Manufacturer |
| Harnesses | Visual check of webbing, stitching and hardware | Before each use; periodic documented inspection | Manufacturer |
| Therapeutic oxygen kit | Cylinder pressure, contents and test date | Before each job | Company policy; federal rules where the dive plan requires oxygen (section 18.25) |
Composite cylinders often have a different test period and a fixed service life. Read the label and the manufacturer’s data. If a cylinder has no readable test date, take it out of service until it is tested.
Worked example: one small spread
Here is how the table turns into dated jobs for a few items. Each job gets its own row, so one item can carry two or more due dates.
| Gear ID | Servicing job | Interval | Last done | Next due |
|---|---|---|---|---|
| CYL-01 | Internal visual inspection | 12 months | 2026-02-10 | 2027-02-10 |
| CYL-01 | Hydrostatic test | 60 months | 2023-03-02 | 2028-03-02 |
| HLM-01 | Annual overhaul | 12 months | 2026-05-20 | 2027-05-20 |
| CMP-01 | Air quality test | 12 months | 2026-01-15 | 2027-01-15 |
| CMP-01 | Filter cartridge change | By running hours | 2026-10-04 | Per hour meter |
| GAU-01 | Test and calibration | 6 months | 2026-08-01 | 2027-02-01 |
Six rows for four items. A spread with 30 items easily carries 70 dated jobs, which is why the schedule needs to be sorted by due date, not by item.
A routine that keeps the schedule moving
Every week
- List everything due in the next 30 days.
- Order the service kits and parts those jobs need.
- Book outside work: hydro testing, air quality testing, factory service.
Before each job
- Check the status of every item going on the truck or the vessel.
- Nothing overdue gets loaded. Tag it out of service and swap it.
- Make sure the service records for that gear can be shown on site.
Every month
- Close out completed jobs: log the date, the result, who did it and the certificate.
- Look for jobs that keep slipping, and find out why.
Every year
- Check your intervals against current manuals and the current edition of your code.
- Retire gear that has reached the end of its service life and remove it from the schedule.
- Confirm you still hold the records your regulator expects. Federal rules require five years.
Common gaps in a dive gear schedule
- One date per item. A cylinder with only a hydro date misses its yearly visual inspection.
- Bailout gear left off. Bailout cylinders and first stages need the same jobs as the main kit.
- Gauges nobody owns. Panel gauges and pneumofathometers get tested only when someone remembers.
- Air testing booked late. Lab results take time. Book the test before the due date, not on it.
- No record of the basis. When an auditor asks why an interval is 12 months, the answer should be in the schedule.
Keeping the schedule
A preventive maintenance schedule only works if someone sees what is coming due. In a spreadsheet that means opening the file every week. When the spreadsheet stops working covers the point where that stops being enough, and PM log or CMMS compares the software options.
GearMaster is set up the same way as this guide. Each item carries its own servicing jobs, such as an annual service, a visual inspection and a hydro, each with its own due date. You get email notice 30 days before a job falls due, and every item shows as Healthy, Impending or Overdue. The features section shows how it works, and pricing lists how many servicing jobs each plan allows per item.